Field-standard reverse osmosis design formulas — size a system, check recovery and scaling risk, and estimate operating cost before you call for a quote.

Design Inputs

Design GPD = peak demand × safety factor, then converted to a per-minute production rate over your planned run window (typically 10–12 hrs/day rather than continuous, to allow CIP and downtime). Safety-factor convention per industry sizing guides — treat as a starting point, not a substitute for engineering review.

System Output

Design Capacity
—
gallons per day, nameplate
Required Production Rate
—
GPM over your run window
Metric Equivalent
—
liters per day

Stream Data

Recovery = permeate ÷ feed flow. Rejection = 1 − (permeate TDS ÷ feed TDS). Typical brackish RO runs 70–85% recovery; seawater RO 35–50%; healthy membranes reject 97–99% of salts.

Performance

Recovery Rate
—
 
Salt Rejection
—
 
Concentration Factor
—
reject-stream concentrating multiple
Concentrate (Reject) Flow
—
GPM

Concentrate Stream Chemistry

Langelier Saturation Index (LSI) on the concentrate stream — always the highest-risk point in the system since recovery concentrates hardness and alkalinity. LSI > 0 signals CaCO₃ scaling risk and typically calls for antiscalant dosing or a lower recovery target. Run concentrate-side numbers, not raw feed water.

Scaling Index

Langelier Saturation Index
—
—
Suggested Antiscalant Dose Range
—
ppm, on concentrate flow — confirm against product data sheet

Cost Inputs

Cost = energy (kWh × rate) + membrane replacement amortized monthly + chemicals/consumables. Typical commercial RO cost mix: power ~35–45%, membranes ~5–10%, chemicals ~5–15%, balance labor/maintenance not modeled here.

Estimated Cost

Monthly Operating Cost
—
Cost per 1,000 Gallons
—
Annualized
—

Flow — GPD → LPD

—

Flow — GPM → m³/day

—

Volume — US Gallons → Liters

—

Pressure — PSI → Bar

—

Formulas follow standard industry sizing and water-chemistry conventions and are provided for preliminary estimating only — final system design should be confirmed by an AMPAC applications engineer.